All Persons Interested In The Elk Grove Triangle Planning Process:
It
has been several weeks since the last public meeting regarding the Elk
Grove Triangle, and we thought it would be helpful to let you know about
the behind-the-scenes work which is under way and what you can expect to
see at the next public workshop. We
hope that this letter also clears up some of the questions and concerns
you may have—if it does not, please feel free to call us (numbers are
provided at the end of this letter).
Direction
from the Planning Commission
At
the January 23, 2003, Planning Commission meeting, the Commission
provided the following direction to staff:
1) The alternatives
developed and discussed at the December and January public workshops
(which generally would allow the splitting of land into 1-acre lots)
were deemed by the Commission to be unimaginative and not responsive to
the needs of the Triangle area. The
Commission directed staff to bring back more alternatives, and to
explore how similar land use issues have been dealt with in other
communities. More on
this later . . .
2) Infrastructure
planning should continue, assuming development with 1-acre lots as a
“worst-case” scenario.
Staff
Work
In
response to the Commission’s direction, Planning staff is engaged in
the following work efforts:
1) We are meeting with
representatives of all of the agencies which provide services to the
area: County water and sewer, Elk Grove Water Service, Elk Grove Unified
School District, and the Elk Grove Community Services District.
Each of these agencies is being asked to identify the facilities
(water and sewer lines, parks, schools, etc.) that would be needed to
support development of the Triangle area.
In addition, Planning staff is coordinating with the City’s
Public Works department on roadway, drainage, and other issues.
2) Based on these
infrastructure needs, Planning staff is preparing an initial cost
estimate of the price of the infrastructure that would be needed to make
development with one-acre lots feasible.
More on this later . . .
3) We are collecting
examples of the types of planning techniques which have been used in
similar rural areas. These
will include clustering, buffers, transitions in lot sizes, etc.
What
to Expect at the Next Triangle Meeting
The
next public meeting will focus on several issues:
1)
Staff will present the results of our discussions with the
various service agencies (water, sewer, schools, parks, drainage, etc.),
and the types of infrastructure which would be necessary to serve the
Triangle area if more development (such as additional 1-acre lot
development occurs in the Triangle area.
2) Staff will present
information on the cost of infrastructure, how these costs would apply
to persons wishing to develop one-acre or larger lots, and how these
costs could be covered. This
portion of the meeting will include an examination of whether
development of one-acre lots throughout the Triangle area appears to be
financially feasible and, if not, what steps would need to be taken to
make this feasible.
3) Staff will present a
variety of alternatives (including the maps generated at the previous
public meetings) for the future development of the Triangle area.
At the direction of the Planning Commission, some of these
alternatives will draw on the experience of other agencies and may not
necessarily provide for equal development opportunity on all of the land
within the Triangle area.
The
meeting will include a discussion of the alternatives, and how each
responds to the general goals for the area (preserving rural character,
etc.)
The
next public meeting has not been scheduled.
Please watch the Planning web site for information on the next
meeting, or call Eric Norris or Steve Flint for the time and date.
Commonly
Asked Questions
The
following are some of the questions we are frequently asked about the
Triangle Area planning process:
Why
is the planning process going so badly?
Hasn’t a decision been made already on land use?
In staff’s view, the planning process is on track and working well.
We hope to provide more information at future meetings which will
make some of the planning issues more clear to everyone involved.
At this point, initial ideas regarding overall goals for the area
have been developed, and a first draft of a land plan for the Triangle
has been prepared. This
first draft is now being refined and “tested” (as discussed earlier)
to see if it is technically and financially feasible—this is not at
all uncommon and is to be expected when dealing with land use issues in
an area like the Triangle.
No
decisions have been made on land use or any other issues.
As noted earlier in this letter, the Planning Commission
specifically asked that more alternatives be developed and presented.
These alternatives will be presented and discussed at a future
meeting.
"Developers"
are dominating the process! Can
the public meetings involve only residents?
Can input from the "developers" be ignored?
The public meetings on the Triangle area are just that—public
meetings. No interested
person can or will be excluded from the discussions.
(In addition, several “developers” are also residents and/or
property owners in the Triangle area.)
At the time the Planning Commission and City Council make final
recommendations and decisions regarding the Triangle area, they will
consider the input from all of the persons involved.
How
could the City adopt a plan that gives some owners one-acre lots and
requires others to maintain larger lot sizes?
While
the City’s land use decisions are required to be based on sound
evidence and to further the City’s goals and policies, it is not
required to maximize the development potential of all land, or to
provide all property owners in a given area with an equal opportunity to
profit from the development of their property.
The City’s General Plan and zoning map, for instance, designate
lands for a variety of uses, some more financially advantageous than
others—two adjacent properties could be designated for different uses
(such as commercial for one parcel and housing for the other) that could
result in a higher value for one of the parcels.
This is a sometimes inevitable outcome of land use planning, and
should not be viewed as a “losers and winners” situation but rather
as a reflection of the fact that the goals of the City may not
correspond with the development goals of every property owner.
Will
there be more voting at the next meeting?
We have not yet decided on the format of the next meeting and how public input
on the various alternatives will be taken and recorded. We
will seek to make sure that everyone’s voice is heard—however, all ideas may
not be reflected in the ultimate plan for the Triangle area. Participants
should be ready to accept that, where different ideas are mutually exclusive,
compromise may be necessary.
Petitions
are circulating in the area. Should
I sign them?
Use your own discretion, but we advise you to be certain that you understand
and agree with the petition before you sign. Planning
staff has not seen the petitions and cannot comment on them; when they are presented
to the City, they will be forwarded to the Planning Commission and City Council
for their consideration.
What
is the difference between “gross” and “net” acres?
Aren’t “gross” lots bigger?
In
simple terms, lots measured on a “gross” basis include both the
buildable area of the lot and any roadways, drainage channels,
etc, that may lie within the lot. At
this time, the Elk Grove Zoning Code measures lots in “Ag Res”
zoning districts based on “gross” acreage.
In
the case of a 1-acre “gross” lot, the buildable area is actually
less than one acre—the rest of the lot is taken up by roads and other
“unbuildable” area. A
1-acre “net” lot has a buildable area of one acre—the roadway that
serves the lot is not included in the lot itself.
So, while both a 1-acre “gross” and “net” lot are each
“one acre,” the gross lot has a smaller buildable area because its
area is measured differently.
How
would switching from “gross” to “net” size affect me?
This depends on your particular situation.
This change (which has not been decided on) could make
it difficult or impossible to split an existing parcel.
For example, if you have a parcel that is 2.00 gross acres
and your zoning is changed to allow one-acre gross lots, you
could potentially split the parcel into two, one-acre lots.
However, if the zoning is changed to require one-acre net
lots, you probably would not have enough land to split into two
parcels—you would need land in addition to the two acres to provide
for roadways, etc.
The
figure at left shows an example of “gross area” lots—each lot
(bounded by the dashed line) in the example has one acre of gross area,
but this includes the roadway in front; the useable area of the lot is
less than one acre. One-acre
lots measured using “net” acres would have one acre of useable area;
the street in front of the lot would not count toward meeting minimum
lot size requirements.
We
hope this letter answers your questions about the Triangle planning
process. If it does not,
please call, write or email us:
|
|
Information on the next public
meeting for the Triangle Comprehensive Plan will be posted on
the Planning web site (www.egplanning.org)
and at city hall. To receive updates on the planning process
via email, send an email to ekramer@elkgrovecity.org and
request to be placed on our mailing list. |
Thank you for your interest in the Triangle
planning process. We look forward to seeing you at future
planning meetings. |
Sincerely, |
Eric Norris, AICP
Elk Grove Planning
|
Steve Flint
Elk Grove Planning
|
|