Phase |
Description of Work |
Anticipated Completion |
Phase 1 |
Construct parking lot and pothole to locate existing utilities |
April 5 – May 13 |
Phase 2 |
- Construct water main and storm drain between Walnut Avenue and School Street
- Construct water main between Elk Grove Florin Road and Walnut Avenue and between School Street and Waterman Road
|
April 5 – July 7 |
Phase 3 |
Demolish south side of roadway between Walnut Avenue and School Street |
June 8 – June 29 |
Phase 4 |
Place asphalt on south side of roadway between Walnut Avenue and School Street |
June 29 – July 21 |
Phase 5 |
Demolish north side of roadway between Walnut Avenue and School Street |
July 21 – August 11 |
Phase 6 |
Construct curb, gutter and sidewalk and place asphalt on the north side of roadway between Walnut Avenue and School Street |
August 11 – September 1 |
Phase 7 |
Construct curb, gutter and sidewalk on south side of roadway between Walnut Avenue and School Street |
September 1 – October 11 |
Phase 8 |
Construct medians |
October 11 – November 1 |
Phase 9 |
Overlay roadway between Elk Grove Florin Road and Walnut Avenue and install pavement dividers |
November 1 – November 23 |